ILLUSTRATIVE / REVIEWABLE / DOWNLOADABLE

Schedule reconciliation sample package

An elevation-only spandrel designation and a missing hardware set recorded as unresolved scope.

ILLUSTRATIVE / EX-01 REV A / NOT FOR FABRICATIONG-01L1L4L2L5L3L612 × 10 ft grossSP-02L1L3L2L48 × 6 ft grossSP-02: absent from schedule; make-up remains pending.
Diagrammatic, not to scale. Gross opening dimensions and shown lite counts match the workbook; fabrication sizes remain unresolved.

Inspect the workbook

This constructed example demonstrates format and reconciliation. It is not a completed client project, a supplier quote or a fabrication schedule.

Includes glass area, framing reference lengths, openings/hardware and an assumptions/RFI register. Unknown specification and procurement values remain blank or pending.

Inside the quantity workbook

OpeningGross size (ft)Shown litesGross area (sq ft)Framing paths (linear ft)
G-0112 × 10612076
SP-028 × 644842

Framing includes perimeter and internal reference paths once. Converted metric columns are available in the workbook. Gross area is not glass order area, and unknown hardware counts remain pending.

What the sample does — and does not — establish

OutputVisible informationRequires project review
GlassGross area and shown lite countsMake-up, bite, edge clearances and fabrication sizes
FramingPerimeter and internal reference pathsProfile widths, joints, cut lengths and stock waste
Openings / hardwareOpening marks and pending hardware setsDoor schedule, ratings and trade responsibility

Example RFI

SP-02 appears on elevation E-02 but is missing from the glass schedule. Quantity is shown only on its gross basis; make-up and price remain pending.

Discuss your project deliverable →